We received comments requesting information regarding the schedule for…
Early right-of-way acquisition is currently underway for the SR 400 Express Lanes project; however, not all right-of-way will be acquired early. The Developer will be responsible for any remaining right-of-way acquisition required as part of their final design in the construction phase. The project’s final design will be completed by the Developer and approved by GDOT in 2024 with right-of-way acquisition extending through 2026. If a property owner would like to sell in advance of the project’s final design, please contact the right-of-way lead, Phil Copeland at pcopeland@hntb.com.